Here are some recent photos of the construction at Jennette's Pier
The ocean was a little rough at the south trestle on Saturday morning as Hurricane Bill made it’s way north, well east of the Outer Banks.
| |
|
|
The Wastewater Treatment building as it appeared on Monday. | |
|
|
The Wastewater Treatment building as it appeared on Friday. | |
South Ramp piles being driven at pile bent #(-1), piles at pile bent #(-2) have been washed down and will be driven next. You can see the east gable end wall of the Wastewater Treatment building in the background. | |
|
|
Six 24”x24’ piles for the Pier House arrived this week (one per trailer load). The 18”x18” pile to the left will be used to finish the south Ramp. | |
|
|
Temporary steel sheet piles installed between the north and south trestle at the dune line (near pile bent line #(-5)). |